December 20, 2007

Main Contractor:
– SINTEX INDUSTRIES LTD
Sub – Contractor Company
– S.G. Mistry
Type of Project
– Government Residential
Type of work
– 1120 EWS Houses
Project Cost In Rs
– 135 Million
Place
– Vastral, Ahmedabad, Gujarat
Note
– R.C.C Civil Work

Boriavi Nagar Palika

May 7, 2009

Main Contractor
– SINTEX INDUSTRIES LTD
Sub – Contractor Company
– S.G. Mistry
Type of Project
– Government Residential
Type of work
– 611 EWS Houses
Project Cost In Rs
– 88.8 Million
Place
– Boriavi, Gujarat
Note
– R.C.C Civil Work

SINTEX INDUSTRIES LTD

April 5, 2010

Main Contractor

Sub – Contractor Company
– S.G. Mistry
Type of Project
– Factory Work
Type of work

Project Cost In Rs
– 58.04 Million
Place
– Namakkal, Tamilnadu

GETCO

May 10, 2010

Main Contractor
– SINTEX INDUSTRIES LTD
Sub – Contractor Company
– S.G. Mistry
Type of Project
– Power Project
Type of work
– 66 Kv
Project Cost In Rs
– 4.1 Million
Place
– Bhalod, Bharuch, Gujarat
Note
– Equipment Foundation, Cable Trench, W.B.M Road

GETCO

May 10, 2010

Main Contractor
– SINTEX INDUSTRIES LTD
Sub – Contractor Company
– S.G. Mistry
Type of Project
– Power Project
Type of work
– 66 Kv
Project Cost In Rs
– 4.1 Million
Place
– Gaudeshwar, Bharuch, Gujarat
Note
– Equipment Foundation, Cable Trench, W.B.M Road

GETCO

May 10, 2010

Main Contractor
– SINTEX INDUSTRIES LTD
Sub – Contractor Company
– S.G. Mistry
Type of Project
– Power Project
Type of work
– 66 Kv
Project Cost In Rs
– 4.1 Million
Place
– Rumkitalav, Navsari Gujarat
Note
– Equipment Foundation, Cable Trench, W.B.M Road

GETCO

January 12, 2011

Main Contractor
– Mirambica Construction Co
Sub – Contractor Company
– S.G. Mistry
Type of Project
– Power Project
Type of work
– 66 Kv
Project Cost In Rs
– 11.97 Million
Place
– Devla, Bharuch, Gujarat
Note
– Equipment Foundation, Cable Trench, W.B.M Road

ARIHANT SUPERSTRUCTURE LTD

April 11, 2011

Main Contractor –

Sub – Contractor Company
– Balaji Superstructure
Type of Project
– Residential Project
Type of work
– 53 EWS Tower, 17 LIG Tower
Project Cost In Rs
– 250 Million
Place
– Chokha, Jodhpur, Rajasthan
Note
– R.C.C Civil Work

ARIHANT SUPERSTRUCTURE LTD

July 17, 2011

Main Contractor –

Sub – Contractor Company
– Balaji Superstructure
Type of Project
– Residential Project
Type of work
– Arihant Adita
Project Cost In Rs
– 89.9 Million
Place
– Gangana, Jodhpur, Rajasthan
Note
– R.C.C Civil Work, 2 BHK, +10 Storied

Arvind Mills & TATA, Arvind and Smart Value Homes LLP

May 21, 2012

Main Contractor –

Sub – Contractor Company
– S.G. Mistry
Type of Project
– Residential Project
Type of work
– 6 LIG Tower
Project Cost In Rs
– 63.03 Million
Place
– Kalol, Gandhinagar, Gujarat
Note
– Civil Work, RCB Technology, Finishing and Plumbing

Adeshwar Realtors

December 5, 2012

Main Contractor –

Sub – Contractor Company
– VESITA INFRATECH
Type of Project – Commercial
– Residential Project
Type of work
– G+12 Storey Tower
Project Cost In Rs

Place
– Pali, Rajasthan
Note
– Civil Work

NRHM, Rajasthan

December 5, 2015

Main Contractor
– SINTEX INDUSTRIES LTD
Sub – Contractor Company
– Balaji Superstructure
Type of Project
– Hospital
Type of work
– 20 Units Pre-Fabricated Hospital
Project Cost In Rs
– 14.42 Million
Place
– Rajasthan
Note
– Plinth Work, Electric & Erection

ARIHANT SUPERSTRUCTURE LTD

July 21, 2016

Main Contractor

Sub – Contractor Company
– S.G. Mistry Construction Pvt Ltd
Type of Project
– Residential Project
Type of work
– 6 Tower, G+4
Project Cost In Rs
– 36.64 Million
Place
– Chokha, Jodhpur, Rajasthan
Note
– R.C.C Civil Work

MPPTCL

August 23, 2016

Main Contractor
– Kalptaru Power Transmission Limited
Sub – Contractor Company
– S.G. Mistry Construction Pvt Ltd
Type of Project
– Power Project
Type of work
– 220kv, 132kv, 33kv,CR Building, W.B.M Road, Substation
Project Cost In Rs
– 34 Million
Place
– Suwasra

Sanganer Enviro Project Development (SEPD)

February 2, 2017

Main Contractor
– Advent Envirocare Technology Pvt. Ltd
Sub- Contractor Company
– M/s Harshad Shah and Co/ S.G. Mistry Construction Pvt Ltd
Type of Project
– Hydraulic Project
Type of work
– Filter Plant, 12.3 MLD
Project Cost In Rs
– 180 Million
Place
– Jaipur, Rajasthan